precautions for the installation of tubular heat exchangers :
1、After the equipment is unpacked, it should be checked item by item according to the packing list. If it does not meet the requirements, the supplier should be contacted to solve it in time.
2、Lifting holes are designed on the equipment for hoisting. Before hoisting, select the wire rope according to the quality marked on the nameplate.
3、The equipment should be placed horizontally, and should be placed in a place where there is no pipeline or other equipment blockage, so that there is an operating space of about 1 meter around the equipment for easy maintenance.
4、If the outlet pressure of the pump is greater than the pressure of the equipment, a pressure reducing valve should be installed in the pipeline where the fluid enters the equipment.
5. If the pressure control valve is assembled, it should be installed on the inlet pipe of the equipment, not at the outlet.